Wednesday, August 20, 2008

Building report - 20th August.

Big developments even though they may not be able to see what they are doing! The niebla, or fog, persists. As we approached the site we had to get to about thirty metres before we could see anything!
The top level now awaits the brick walls, the concrete slab or floor will be the final act of the building program.
The second level will be the kitchen and below that will be the storage area and toilets. This latter area has yet to be defined by the builders, however, the way they are progressing I am sure it will be there next week.


They are presently boxing up the foundations for the kitchen area and then they will fill it by wheelbarrow to the level of where the men are working! As you can see it will be lower than the main community area.